The wind power plant for electricity production called "Serra del Gelo Wind Farm" is located in the municipality of Cortale (CZ).
The area covered by the planting has an area of about 60 Ha, spreads along a mountain ridge at an average altitude of 830 to 870 meters above sea level.
The plant consists of n. 7 Gamesa mod. G52 850 kW wind turbines with a hub height of 65 m and a rotor diameter of 52 m, for a total rated capacity of the wind farm of 5.95 MW.
The plant appears to be connected to a MV line and all the wind turbines are connected to the same substation located in loc. Crati in the municipality of Cortale.
5,95 MW
7 Towers installed
08 september 2006
W-energy Srl
Eni Plenitude Technical Services
Eni Plenitude Technical Services